Local development scheme

Information about what the local development scheme is, which documents are included, and what the timescale for completion is. 

What is the Local Development Scheme (LDS)?

The Local Development Scheme (LDS) sets out the documents we will prepare as part of the Local Plan over the next 3 years.

Our LDS provides the community and other partners with information on the different Local Plan documents for the area, as well as the timescale, the associated work programmes, budgeting and resources required to produce each document.

The revised Local Development Scheme for the period 2018-2021 was agreed by the council's Cabinet on 4 September 2018. 

Local Development Scheme 2018-2021 (pdf 3.1mb opens in new window)

See below for the latest timetable for completing the various documents of the Local Plan.

What is the timescale for completing the Local Plan?

The latest timetable for each of the documents making up the Local Plan is set out below:

Strategy Document

Issues and Options – Complete 2008
Preferred Approach – Complete 2010
Further Consultation - Complete November-December 2011
Draft Strategy - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission – Complete March 2014
Submission – April 2014
Independent Examination – Complete October-November 2014
Modifications consultation - March - May 2015
Inspector's report - received January 2016
Adoption – April 6 2016

Allocations Document

Potential Sites – Complete 2010
Draft Allocations - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission – Complete March 2014
Submission – April 2014
Independent Examination – Complete October-November 2014
Modifications consultation - March - May 2015
Additional modification (Site SMB-B) - Jan-Feb 2016
Inspector's report - received June 2016
Adopted – July 27 2016

Bridlington Town Centre Area Action Plan

Issues and Options – Complete 2006
Preferred Options – Complete 2007
Second Preferred Options – Complete 2009
Publication – Complete 2010
Submission – Complete 2011
Independent Examination – Complete December 2011 and May 2012
Adopted – February 2013

Joint Minerals Local Plan

Issues and Options – Complete 2008
Preferred Approach – Complete 2010
Site Selection and Additional Sites - Complete early 2012
Second Preferred Approach - Complete Summer 2016 
Publication – Complete April 2018
Submission – Complete July 2018 
Examination – January 2019
Adoption – Expected Summer 2019

Joint Waste Local Plan

Please see Hull City Council's website to see timescales for the Plan's preparation.

The Statement of Community Involvement and the Local Development Scheme have been completed. A number of Annual Monitoring Reports have also been prepared since 2005.

Local Plan Review

The Local Development Scheme (LDS) sets out the following timetable for a Local Plan Review: 

Options - Expected late 2018
Draft Local Plan - Expected early 2020
Publication - Expected early 2021
Submission - Expected mid-2021