A164 Humber Bridge to Beverley Route Improvement Scheme - 5 year review

Results
Consultation period
1 Dec 2018 - 22 Jan 2019
Area
Any Area
Target audience
Users of the A164
What you told us
The survey was well received with 334 responses.  It was noted that congestion at Skidby and Castle Hill roundabouts is considered to have reduced, at Willerby Hill Business Park it is considered about the same as before, whilst at Willerby Roundabout congestion has not reduced. 
 
When considering journey times, feedback suggests that these may not have reduced as projected, whilst safety along the route has improved and there is a marked improvement in facilities for pedestrians and cyclists.
What we did next
The feedback provides data aimed at demonstrating the effectiveness of the A164, Humber Bridge to Beverley Route Improvement Scheme in meeting its objectives/outcomes five years after completion of the works. 
 
This feedback will be incorporated into the five-year review of the scheme reporting on the scheme objectives/outcomes, which aims to demonstrate that investment for the scheme has provided value for money and to ensure lessons are learnt to inform future decision making.
Further information
For further information, please see the attached summary document.
Download full results
A164 Feedback Report - 518KB A164 Feedback Report